Willow Pond Dam

Design & Permitting
Peterborough, New Hampshire

Due to a breach in a section of the earthen Willow Pond Dam, a significant portion of the pond was lost.  The Turner Group was retained to design and permit the project through the New Hampshire Department of Environmental Services.  The majority of the 10’ high x 200’ long earthen section of the dam was reconstructed, and a new 20’ wide concrete spillway with low level control was added and the 12 acre pond was fully restored.