Bidder #1 Bidder #2 Bidder #3 Bidder #4 Bidder #5 Bidder #6 Apparent Low Daedalus Estimate Variance A/E Opinion of $ Variance
General Contractor                      
Bidder Fontaine Brothers, Inc. Suffolk Construction Co., Inc. Consigli Construction Co., Inc. Bacon Construction Co., Inc. Jan Five Corp. dba Alexandra Construction Eastern Contractors, Inc.          
Bid Deposit X X X X X X          
Addenda 1, 2, 3 Acknowledged X X X X X X          
DCAM Certificate X X X X X X          
DCAM Update X X X X X X          
Item 1 Work by GC Total $13,243,094 $11,945,094 $13,328,970 $11,898,794 $12,564,070 $12,812,094          
Item 2 Work by Sub-bids $14,997,906 $14,997,906 $14,996,030 $14,997,906 $15,018,930 $15,104,906          
Base Bid $28,241,000 $26,943,000 $28,325,000 $26,896,700 $27,583,000 $27,917,000 $26,896,700 $27,817,092 ($920,392) $28,098,806 ($1,202,106)
(Automatic Numeric Check of Base Bid) $28,241,000 $26,943,000 $28,325,000 $26,896,700 $27,583,000 $27,917,000       $561,976 Contingency
Ranking 5 2 6 1 3 4       $28,660,782 ($1,764,082)
NOTES                      
Alternate # 1 "Green Schools" $94,000 $120,000 $96,600 $105,000 $89,000 $100,000          
Alternate # 2 Track lighting & PA $88,000 $102,000 $118,900 $84,000 $140,000 $100,000 Rejected        
Alternate TOTAL $182,000 $222,000 $215,500 $189,000 $229,000 $200,000          
Base Bid $28,241,000 $26,943,000 $28,325,000 $26,896,700 $27,583,000 $27,917,000          
Grand TOTAL with Alternate 1 only       $27,001,700              
Grand TOTAL with ALL Alternates $28,423,000 $27,165,000 $28,540,500 $27,085,700 $27,812,000 $28,117,000